This OCR scan may contain automatically generated text as generated using Apache Tika and Tesseract. It may not be correct. No effort has been made to correct any of these scans (so far). These OCR scans are also used in the site's Search feature. Please review the Search Policy for details about the site features. The OCR scan is provided here for reference purposes. It provides searchable text when the underlying document might not. But the scan process may not always work perfectly.

COMMONWEALTH OF VIRGINIA DEPARTMENT OF MINES, MINERALS AND ENERGY

DIVISION OF MINED LAND RECLAMATION P.O. DRAWER 900, BIG STONE GAP, VA 24219

TELEPHONE: (276) 523-8198

ABANDONED MINE LAND INSPECTION

DMLR-AML-130S Printed: 10/01/21 5/06 Page 1 of 1

HNM0009816

PROJECT NAME PROJECT NO. GRANT YEAR REPORT NUMBER

Project Reclaim Phase II 91806 2018 HNM0009816

CONTRACT INFORMATION

CONTRACT NUMBER EXPIRATION DATE PERCENT OF CONTRACT COMPLETED

        90 

CONTRACTOR NAME ENGINEER NAME

SITE CONTACT PERSON: Kevin Large

INSPECTION DATE ARRIVAL DEPARTURE GROUND CONDITION

09/14/21 02:30 PM 03:30 PM DRY

INSPECTION BY ATTACHMENTS

MCDONALD-TAYLOR, H.

COMMENTS

The contract for Project Reclaim Phase II was signed on 12/28/21 and a Notice to Proceed was issued the same day.
Work at the site was already on going from Project Reclaim Phase I. Material haulage transitioned from Phase I to Phase II on the day the contract was signed. Work at the site is complete. Seeding of the structure will occur under the 2021 Revegetation Project. This inspection was conducted as a bid showing for the revegetation project.

COMMONWEALTH OF VIRGINIA HNM0009816

DEPARTMENT OF MINES, MINERALS AND ENERGY Dh DIVISION OF MINED LAND RECLAMATION

P.O. DRAWER 900, BIG STONE GAP, VA 24219 Virginia Depay TELEPHONE: (276) 523-8198

Mines Minerals and Energy ABANDONED MINE LAND INSPECTION

PROJECT NAME, PROJECT NO, GRANT YEAR | REPORT NUMBER Project Reclaim Phase Il 91806 2018 HNM0009816 CONTRACT INFORMATION CONTRACT NUMBER EXPIRATION DATE, PERCENT OF CONTRACT COMPLETED 90 CONTRACTOR NAME ENGINEER NAME,

‘SITE CONTACT PERSON: Kevin Large

INSPECTION DATE, ARRIVAL DEPARTURE. GROUND CONDITION 09/14/21 (02:30 PM 03:30 PM DRY INSPECTION BY ATTACHMENTS

MCDONALD-TAYLOR, H.

‘COMMENTS

The contract for Project Reclaim Phase Il was signed on 12/28/21 and a Notice to Proceed was issued the same day. Work at the site was already on going from Project Reclaim Phase |. Material haulage transitioned from Phase | to Phase Ion the day the contract was signed. Work at the site is complete. Seeding of the structure will occur under the 2021 Revegetation Project. This inspection was conducted as a bid showing for the revegetation project.

DMLR-AML-130S Printed: 10/01/21 5/06 Page 1 of 1